Rehabilitation of M-3, Margara-Vanadzor-Tashir-Georgian Border interstate road km127+900-km130+400 section Rehabilitation of M-14,M-4-Shorzha-Vardenis intestate road km19+450 - km39+400 section Rehabilitation of M-1, Yerevan-Gyumri-Georgian border interstate road km134+500 to km141+500, and from km143+300 to148+300 sections Rehabilitation of M-6 Vanadzor-Alaverdi-Georgian border interstate road section km48+140- km62+300

Rehabilitation of M-6 Vanadzor-Alaverdi-Georgian border interstate road section km48+140- km62+300

On October 20th, 2018, AAB Construction received the construction permission for rehabilitation of M6 Vanadzor-Alaverdi-Georgian border interstate road section km48+140- km62+300. Earlier we have won the tender of rehabilitation of this road section announced by TPIO and financed by Asian Development Bank. The scope of works includes:

 

The planned duration to complete the project is 900 days. To ensure the smooth and safe traffic as well as to raise the efficiency of the works the process will be implemented part by part. All the safety measures are kept to the maximum, the road is equipped with warning signs, night lights, and flashlights.